WELCOME
The MESA LTD Trust has been created by like minded Leaseholders & Residents to effect positive change and improvement to the site for the benefit of everyone, whilst working closely with our site management team FSPM This website has been designed to provide all the information you need to reside at Marks Court

ABOUT
About Us
The MESA LTD Trust consists of 5 Volunteer Directors who all own a property at Marks Court We meet in person once a month to continue to work for the benefit off all leaseholders & residents.
Updates from our meetings will be posted to the Bulletin Board page to keep you up to date with the progress we are making
WORKS
Scheduled Works
Planned Maintenance for 2025
December 24
4th November 24
1st August 24
25th June '24
17th June '24
April '24
March '24
Planned Maintenance for 2025
-
Pavement rehabilitation
-
Brickwork repairs
-
Renewal of bin store doors
-
Replace communal lights
-
Tree management (survey & establish 5-yr rolling program)
-
Replacement of Meter Cupboard door
-
Fire door remedial works
-
Painting of rear entrance/exit porches
Portico Maintenance
The Portico refurbishment is nearing completion. The final block will be completed w/c 9th December
Fibre Installation
Hyperoptic are continuing to install the fibre optic network around the estate and in to each block. The works are scheduled for completion end of Jan / beginning of Feb 2025
Fibre Installation
Fibre Installation Hyperoptic have started the fibre installation at Marks Court. At this point the MESA LTD trustees are waiting on further information from Pier Management to confirm the planned schedule of works and what impact (if any) can be expected. There is no charge for the installation of services to each property. Once complete every leaseholder will have the opportunity to select a service provider who will charge accordingly for their services.
Planned Building Works Update
From Pier Management
We have now received
-
Building control notice
-
Pre-commencement condition discharge for the Construction Management Plan
-
Structural engineers foundation details
-
Topographical survey
We will at the end of this week dig and re-fil with concrete 1No foundation. Works will commence on Thursday with site set up and marking out of the area in question. Materials etc will likely be delivered on Friday. Excavation will occur on Monday and concrete will be poured on Tuesday. The attached traffic management plan details the location of the works.
In respect of machinery there will be a small digger on site followed by a concrete delivery. The usual working hours will apply. I don’t believe there will be any working over the weekend for this portion of construction. The area will be temporarily fenced off whilst this work is ongoing and on completion the site will be made good. We are happy to discuss the potential moving of the rose beds elsewhere within the gardens.
Planned Building Works
As many of you will already be aware the Freeholder has obtained planning permission to develop the area of Marks Court known as the Rose Garden with the erection of an additional 3 storey block comprising 4 self-contained flats.
Details of the development can be found via Southend City Council’s web planning portal, which may be accessed at www.publicaccess.southend.gov.uk/online-applications and searching using the following reference 21/00641/FUL. Planning permission was granted back in July 2021 and to avoid permission lapsing, the Freeholder is required to make a material start of the project within 3 years of permission having been granted.
Without any prior notice having been given to either Marks Estate Southchurch Avenue Co Ltd (MESA LTD) or Fowler & Spenceley Property Management (FSPM) as MESA’s agent, the freeholder’s surveyors were on site last week carrying out some initial site investigations into existing services within the vicinity of the new building. The surveyors were challenged whilst on site by one of the MESA Board members and by several other residents, at which time they confirmed the purpose of their visit.
Subsequently Pier Management, as the Freeholder’s agent, advised that it was their client’s intention to commence work on site on the 26th June 2024. It is understood that this work will include the fencing off of the site and the excavation of the foundations. This is, as mentioned above, primarily to ensure that the planning permission they hold does not expire. Although Pier have given assurances that it is the Freeholder’s intention that this work will be undertaken with the minimum of inconvenience to residents no further detail has been provided.
This is not a project that is supported by MESA LTD who, having taken independent legal advice, understand that although there are restrictions within the Trust Deed that prohibit extending the existing buildings, there is nothing which prevents the Freeholder from building an entirely separate, additional residential block. Both MESA LTD and FSPM will be keeping a close watch on the development, both during this initial phase and as it progresses, to ensure any disruption to residents is kept to a minimum and where necessary, will be bringing any concerns to the attention of Pier Management.
Requests have been submitted via FSPM to Pier Management to obtain further details of these works, to include:
* A copy of the relevant Health & Safety documents.
* Details of the project insurance.
* A method statement detailing how disruption will be minimised during any construction works and how the existing roadways and parking facilities are to be protected and kept clean.
* How the residents are to be compensated for the loss of the rose garden and whether there are plans for it to be relocated at the Freeholder’s expense elsewhere on the Court.
* A timeline for the proposed works
We will provide further updates as and when additional information is made available to us.
Fibre Upgrade
FSPM and the MESA Trustees are currently working with a number of service providers to install Marks Court with full fibre connectivity to every property A number of site surveys have already taken place and are under consideration The installation will make use of the current infrastructure to keep disruption to a minimum There will be no cost for the initial site installation Dates & schedule of works to be confirmed shortly
FSPM Site Visit
FSPM and one of the MESA Trustees were onsite Thursday 28th March to carry out the first of the regular dilapidation surveys
Images can be found here: Survey 28th March 24
BULLETIN
Bulletin Board
Final Deadline – Parking Registration Required by midday Friday 12th December
Dear Residents We are now finalising the new parking system and preparing to issue the parking app. A number of apartments have still not provided their details to FSPM. This is the final reminder. You must send the following information to Rob at FSPM ( Robert@FSPM.co.uk ) by midday Friday 12th December: Your full name Flat number Car make and model Car registration number(s) Mobile number Email address If you do NOT have a car: You still must provide your name, flat number,
Sunday's AGM
Leaseholders Annual General Meeting The MESA AGM will be held on Sunday 7th December at the Park Inn Southend @ 10am. The Park Inn Southend On Sea The Directors will be providing the following updates including but not limited to: Financial Overview 2025 Accounts 2026 Budget Transfer of funds from Woods Service Charge Projects Undertaken in 2025 Painting of Porticos Bin Locker Doors Communal Lighting Brickwork Repairs Projects Proposed for 2026 Communal Window Repairs
Car Parking Announcement
Message from FSPM - Car Parking To All Marks Court Owners and Residents Parking management at Marks Court will be reinstated from Monday 1st December. NPC, the parking management provider, has introduced a new web-based app that will allow residents to book visitor parking spaces more easily. You will receive a download link and usage instructions directly from NPC before 1 December. To set up your access, we must share residents’ and owners’ email addresses with NP
May '25
Fibre Installation Hyperoptic are in the final stages of completing the installation across the site. In the next few weeks all residents will receive a leaflet drop providing details of how to connect your property. Bin Doors Work is ongoing to replace bin doors that are dilapidated and in need of repair. The work will continue to ensure all are repaired, painted and matching. Tree Survey FSPM along with a Tree Surgeon will be surveying the site shortly to c
February '25
House Rules Community Living Guidelines
19th January '25
Leaseholders AGM Minutes The presentation and meeting minutes are now available >> Meeting Minutes Meeting Presentation Fibre Installation Hyperoptic are continuing to install the fibre optic network around the estate and in to each block, a MESA LTD trustee will be meeting with FSPM & Hyperoptic on Monday 20th Jan to discuss the final installation plan and projected completion date.
9th December 24
Leaseholders AGM Thank you to everyone who attended the Leaseholders Annual General Meeting on Sunday at The Park Inn hotel. The presentation and meeting minutes will be available shortly.
December 24
Portico Maintenance The Portico refurbishment is nearing completion. The final block will be completed w/c 9th December Fibre Installation Hyperoptic are continuing to install the fibre optic network around the estate and in to each block.The works are scheduled for completion end of Jan / beginning of Feb 2025